Projects : BEL and Kuvempu circle underpass
Finish Editing
Save
Undo
Clear
Agency
: Bangalore Development Authority
Budget
: Rs.39.93 Crores
Estimated time
: 15 months
Start date
: 09-09-2009
End date
: 30-08-2014
Description
BEL and Kuvempu circle underpass - details as on 30.12.2011
Sl.No. Items Project Details
1 Project Name Construction of underpadd along ORR at BEL and Kuvempu circles
  Owner Name BANGALORE DEVELOPMENT AUTHORITY
3 Financing KUIDFC
4 Architect/Consultant M/s. MANASA CONSULTANTS, Malleswaram, Bangalore
5 Contractor M/s. PJB CONSTRUCTIONS
6 Project start date 09/09/2010
7 Project duration 15 months
8 Project cost Rs.39.93 Crores
9 Amount released till date Rs.12.76 Crores
10 Sub-contractor details (If any) Nil
11 Percentage of work completion 40%