Agency
: Bangalore Development Authority
Budget
: Rs.41.72 Crores
Estimated time
: 15 months (extended upto 22/12/2011)
Start date
: 02-08-2019
End date
: 02-08-2019
Description
Sl.No. | Items | Project Details |
1 | Project Name | Construction of Grade Separator at HSR 14th main, Bellandur and Devarabeesanahalli (Pkg-1) along ORR |
2 | Owner Name | BANGALORE DEVELOPMENT AUTHORITY |
3 | Financing | KUIDFC |
4 | Architect/Consultant | M/s. STUP CONSULTANTS PVT. LTD., |
5 | Contractor | M/s. SIMPLEX INFRASTRUCTURE LIMITED |
6 | Project start date | 09/09/2009 |
7 | Project duration | 15 months (extended upto 22/12/2011) |
8 | Project cost | Rs.41.72 Crores |
9 | Amount released till date | Rs.19.00 Crores |
10 | Sub-contractor details (If any) | Nil |
11 | Percentage of work completion | 60% |