Projects : Kadubeesanahalli underpass
Finish Editing
Save
Undo
Clear
Agency
: Bangalore Development Authority
Budget
:
Estimated time
:
Start date
:
End date
:
Description
Kadubeesanahalli Flyover- details as on 17.12.2011
Sl.No. Items Project Details
1 Project Name Construction of underpass/grade separator along ORR at Kadubeesanahalli junction
2 Owner Name BANGALORE DEVELOPMENT AUTHORITY
3 Financing KUIDFC
4 Architect/Consultant M/s. NAGESH CONSULTANTS
5 Contractor M/s. SIMPLEX INFRASTRUCTURE LIMITED
6 Project start date 03/03/2010
7 Project duration 15 months
8 Project cost Rs.39.80 Crores
9 Amount released till date Rs.17.58 Crores
10 Sub-contractor details (If any) Nil
11 Percentage of work completion 48%