Projects : Mahadevapura Flyover
Finish Editing
Save
Undo
Clear
Agency
: Bangalore Development Authority
Budget
:
Estimated time
:
Start date
:
End date
:
Description
Devarabeesanahalli Flyover- details as on 17.12.2011
Sl.No. Items Project Details
1 Project Name Construction of flyover along ORR at Mahadevapura junction
2 Owner Name BANGALORE DEVELOPMENT AUTHORITY
3 Financing KUIDFC
4 Architect/Consultant M/s. NAGESH CONSULTANTS
5 Contractor M/s. SIMPLEX INFRASTRUCTURE LIMITED
6 Project start date 01/03/2010
7 Project duration 15 months
8 Project cost Rs.38.67 Crores
9 Amount released till date Rs.19.33 Crores
10 Sub-contractor details (If any) Nil
11 Percentage of work completion 86%